Scope of work
During the installation of a substation jacket, Scanmudring was engaged to fill and pump gravel inside the jacket, preventing erosion around the spudcans.

A rock dumping vessel had placed scour protection around the jacket, but the inside still needed filling. The ScanCrawler placed gravel around the spudcans while the 15Te Scanmachine fed it from outside, working inside the structure in 11 days.

During the installation of a substation jacket, Scanmudring was engaged to fill and pump gravel inside the jacket, preventing erosion around the spudcans.

Once the jacket was installed, a rock dumping vessel placed scour protection around the outside, but rock installation was still needed within the structure itself. The wind farm operator, a long-standing Scanmudring client, approached us for an efficient method of securing the area inside the jacket, particularly around the buckets.
Specific Tooling
The ScanCrawler had been used inside structures before and was selected to place the rock. The 15Te Scanmachine fed the ScanCrawler with gravel pre-dumped out inside the jacket.


SIMOPS using both the Scanmachine and Scancrawler.
The method statement had the Scanmachine working the pre-dumped gravel outside the structure, with its exhaust connected to the ScanCrawler, which placed the rockdump inside the jacket.
.webp)
