Scope of work
In support of a P&A and platform removal campaign, Scanmudring relocated a total of 6,961 m3 of rockdump to support the footprint of a drilling rig at two locations. The operation was planned to DNV design criteria, fulfilling foundation stabilisation while minimising seabed disturbance.
Environmental constraints at both locations meant that, so far as reasonably practicable, additional gravel had to be avoided and seabed disturbance kept to a minimum throughout.
The underlying principle was to re-form the highest parts of the berms and push the peaks into the adjacent troughs. This reduced overall berm thickness and, where necessary, removed side walls and the outer edges of top pad arrangements (scalloping), re-depositing that rock within the footprint of the proposed berm de
sign.

.jpg)



.webp)