Scope of work
The project was carried out across five offshore foundation areas in the North Sea, where Scanmudring removed soil plugs from piles prepared for offshore energy infrastructure.
The scope covered soil plug removal from 20 foundation piles across five offshore areas, with four piles in each area. The plugs were dredged to the specified depths, after which each pile was cleaned with high-pressure water jets and inspected. Across the campaign, the recorded dredged depth totalled approximately 74 m, the removed volume was about 174 m³, and recorded dredging time was around 179 hours.
Soil resistance ranged from approximately 80 to 800 kPa. SPRT03 was therefore configured with the Clay Cutter as the primary module, supported by suction and high-pressure cleaning. A Rock Cutter was mobilised as a contingency for harder material or obstructions, but it was not required during the documented campaign.






